Factory acceptance
Machine identity, workmanship, available functions, agreed format tests, documents, accessories and shipment readiness.
Pre-shipment acceptance
A factory acceptance test, or FAT, should compare the finished bottled water filling equipment with the approved order basis before shipment. Use this page to define test materials, observable functions, evidence, open points and the boundary between factory testing and site commissioning.
A useful FAT begins with controlled project documents. Agree what can be demonstrated at the factory, which bottle and pack formats are available, and what must wait for the final site utilities and complete-line installation.
| Control Item | Record Before FAT | Why It Matters |
|---|---|---|
| Approved order scope | Machine list, model, quantity, options, interfaces and latest approved revisions. | Prevents inspection against an outdated quotation. |
| Reference formats | Bottle drawings, samples, neck finish, cap, label and pack format included in the test. | Defines which change parts and handling conditions can be observed. |
| Output basis | Reference bottle, stated speed basis, test duration, planned stops and available downstream scope. | Separates a stated rating from the conditions actually demonstrated. |
| Test materials | Quantity and source of bottles or preforms, caps, water, labels, film, cartons and coding consumables. | Avoids an incomplete test caused by missing buyer materials. |
| Factory utilities | Available power, air, water, drainage and temporary equipment used for the test. | Explains differences from the final site conditions. |
| Acceptance points | Observable function, tolerance or document evidence for each contracted requirement. | Makes pass, deviation and not-tested decisions traceable. |
| Witness and authority | Buyer and supplier representatives authorized to record results and actions. | Avoids informal comments being mistaken for final approval. |
| Shipment release rule | Required closures, accepted punch-list items and documents needed before packing. | Connects FAT results to a controlled shipping decision. |
Work through each group with the approved specification beside you. A checked item means it was reviewed; it does not automatically mean the requirement passed. Record the result and evidence in the project FAT report.
Use the printed page with the controlled FAT report. Checking an item records review progress only; acceptance requires the agreed result and evidence.
Performance observations are meaningful only when the format, duration, materials, available line scope and interruptions are recorded. Do not convert a short factory demonstration into a guaranteed site output unless the contract explicitly defines that basis.
| Observation Area | Record | Evidence Example |
|---|---|---|
| Test arrangement | Machines connected, temporary interfaces and unavailable packages. | Marked layout or test-boundary sketch. |
| Format and materials | Bottle, cap, label or pack versions and material quantities. | Sample identifiers and photographs. |
| Operating window | Start time, stop time, planned interruptions and operator actions. | Time log and event notes. |
| Output observation | Counter basis, good/rejected sample logic and stated limitations. | Counter photographs or exported records where available. |
| Quality observations | Fill level, cap application, leakage, label or pack observations as agreed. | Sample sheet, measurements and photographs. |
| Stops and recovery | Alarm, cause, response and restart behavior observed. | Alarm log and video segment reference. |
| Unverified items | Functions that require final site utilities, materials or complete-line integration. | Site acceptance carryover list. |
A verbal promise is not a closure record. The final report should identify the requirement, observation, disposition, owner, due date and evidence used to close each item.
| Field | Question to Answer | Closure Standard |
|---|---|---|
| Requirement | Which approved specification, drawing or order item applies? | Reference is exact and revision-controlled. |
| Observation | What was seen, measured or unavailable? | Statement is factual and location-specific. |
| Classification | Deviation, incomplete work, document gap, site carryover or observation? | Category determines release and follow-up. |
| Disposition | Correct, accept, retest, defer to site or revise document? | Buyer and supplier authorities agree in writing. |
| Evidence | What proves the action was completed? | Photo, video, measurement or controlled document is linked. |
| Status | Open, conditionally accepted, closed or carried to site? | Final status and responsible person are recorded. |
FAT checks the manufactured equipment under the agreed factory conditions. Site acceptance and commissioning confirm final utilities, installed conveyors, local materials, operator training and sustained operation in the buyer plant. The order should state which results belong to each stage.
Machine identity, workmanship, available functions, agreed format tests, documents, accessories and shipment readiness.
Final positioning, utilities, complete-line interfaces, local materials, training and correction of installation issues.
Contract-defined operation and quality checks under the final plant conditions and agreed responsibility boundary.
The reference below is provided for buyer context. It describes a Krones factory acceptance test service and does not define AllotTech equipment, scope, affiliation or guaranteed results.
Buyer questions
It should compare machine identity, approved scope, workmanship, safety functions, controls, bottle handling, rinsing, filling, capping, available downstream functions, documents, accessories and packing readiness against the agreed order basis.
Not automatically. Record the reference bottle, materials, connected machines, test duration, interruptions and factory utilities. Final site output may also depend on installed conveyors, local materials, operators, utilities and complete-line integration.
Confirm the agreed quantities and versions of bottles or preforms, caps, water, labels, coding consumables, film and cartons. The exact materials depend on the ordered equipment and formats selected for FAT.
FAT reviews the manufactured equipment under agreed factory conditions. Site commissioning and acceptance review the finally installed line with site utilities, local materials, trained operators and the contractual site-test basis.
Only according to the agreed release rule. Items should be classified as shipment-blocking, accepted punch-list work or site carryover, with responsible persons, due dates and written evidence requirements.
Give every item a unique number, requirement reference, factual observation, photo or measurement where appropriate, classification, owner, target date, disposition and closure evidence.